[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118751":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118751,789,1,"单选题","关于进度计划编制和调整的说法，错误的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总进度规划、项目子系统进度规划与项目子系统中的单项工程进度计划之间的联系和协调",false,{"key":16,"text":17,"correct":18},"B","预测性进度规划、指导性进度规划与实施性进度计划之间的联系和协调",true,{"key":20,"text":21,"correct":14},"C","设计方编制的进度计划、施工和设备安装方编制的进度计划与采购和供货方编制的进度计划之间的联系和协调",{"key":23,"text":24,"correct":14},"D","业主方编制的整个项目实施的进度计划与采购和供货方编制的进度计划之间的联系和协调","2021\u002F2020教材P130页 在建设工程项目进度计划系统中各进度计划或各子系统进度计划编制和调整时必须注意其相互间的联系和协调，如： (1)总进度规划（计划）、项目子系统进度规划（计划）与项目子系统中的单项工程进度计划之间的联系和协调； (2)控制性进度规划（计划）、指导性进度规划（计划）与实施性（操作性）进度计划之间的联系和协调； (3)业主方编制的整个项目实施的进度计划、设计方编制的进度计划、施工和设备安装方编制的进度计划与采购和供货方编制的进度计划之间的联系和协调等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]