[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118748":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118748,789,1,"单选题","施工方所编制的下列计划都与施工进度有关，但属于项目管理范畴的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","企业年度生产计划",false,{"key":16,"text":17,"correct":14},"B","企业月度生产计划",{"key":19,"text":20,"correct":14},"C","企业旬生产计划",{"key":22,"text":23,"correct":24},"D","分部分项工程进度计划",true,"2021\u002F2020教材P131页 建设工程项目施工进度计划，属工程项目管理的范畴。而P130的表2z103021与施工进度有关的计划中年月旬是施工企业的生产计划。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]