[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118746":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118746,789,1,"单选题","建设工程项目进度计划系统是由多个相互关联的进度计划组成的系统，作为项目进度控制的依据，此系统的建立和完善是在()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目立项决策时",false,{"key":16,"text":17,"correct":14},"B","项目设计阶段",{"key":19,"text":20,"correct":14},"C","项目施工准备阶段",{"key":22,"text":23,"correct":24},"D","项目进展过程中",true,"2021\u002F2020教材P129页 三、建设工程项目进度计划系统 建设工程项目进度计划系统是由多个相互关联的进度计划组成的系统，它是项目进度控制的依据。由于各种进度计划编制所需要的必要资料是在项目进展过程中逐步形成的，因此，项目进度计划系统的建立和完善也有一个过程，它是逐步完善的。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]