[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118745":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118745,789,1,"单选题","按照建设工程项目总进度目标论证的工作步骤，在调查研究和收集资料之后应进行的步骤是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进行项目结构分析",true,{"key":16,"text":17,"correct":18},"B","确定项目工作编码",false,{"key":20,"text":21,"correct":18},"C","编制各层进度计划",{"key":23,"text":24,"correct":18},"D","进行进度计划系统的结构分析","2021\u002F2020教材P129页 建设工程项目总进度目标论证的工作步骤是： （1）调查研究和收集资料 （2）进行项目结构分析 （3）进行进度计划系统的结构分析 （4）确定项目的工作编码→编制各层(各级)进度计划 （5）协调各层进度计划的关系和编制总进度计划 （6）若所编制的总进度计划不符合项目的进度目标，则设法调整 （7）若经过多次调整，进度目标无法实现，则报告项目决策者。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]