[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118744":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118744,789,1,"单选题","关于建设工程项目进度计划系统的说法，错误的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设工程项目进度计划系统是项目进度控制的依据",false,{"key":16,"text":17,"correct":14},"B","项目各参与方可以编制多个不同的建设工程项目进度计划系统",{"key":19,"text":20,"correct":14},"C","建设工程项目进度计划系统是由多个相互关联的进度计划组成的系统",{"key":22,"text":23,"correct":24},"D","项目进度计划系统是在初步设计阶段完善的",true,"2021\u002F2020教材P129页 建设工程项目进度计划系统是由多个相互关联的进度计划组成的系统，它是项目进度控制，的依据。项目进度计划系统的建立和完善有一个过程，它也是逐步完善的。由于项目进度控制不同的需要和不同的用途，业主方和项目各参与方可以编制多个不同的建设工程项目进度计划系统。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]