[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118741":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118741,789,1,"单选题","某建设工程项目采用项目总承包模式，则该项目的总进度目标由()控制。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","业主方",true,{"key":16,"text":17,"correct":18},"B","总承包方",false,{"key":20,"text":21,"correct":18},"C","设计方",{"key":23,"text":24,"correct":18},"D","监理方","2021\u002F2020教材P128页 建设工程项目总目标的控制是业主方项目管理的任务（若采用建设项目总承包的，协助业主进行项目总进度目标的控制也是建设项目总承包方项目管理的任务）。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]