[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118738":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118738,789,1,"单选题","在冬季长，施工期短的北方高纬度地区，采用预制混凝土技术可充分利用混凝土构件非施工期的工厂制作和施工期的快速现场安装，而现场浇捣混凝土则养护时间较长，因此，在施工进度控制技术措施中，涉及对实现施工进度目标有利的（）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","控制技术",false,{"key":16,"text":17,"correct":14},"B","合同结构",{"key":19,"text":20,"correct":14},"C","组织结构形式",{"key":22,"text":23,"correct":24},"D","设计技术和施工技术",true,"2021\u002F2020教材P151页 施工进度控制的技术措施涉及对实现施工进度目标有利的设计技术和施工技术的选用。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]