[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118737":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118737,789,1,"单选题","施工方进度控制的管理措施涉及管理的思想、方法、手段以及承发包模式、合同类型与风险管理等。其中，工程承发包模式主要影响()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工作之间的逻辑关系",false,{"key":16,"text":17,"correct":18},"B","工程实施的组织与协调",true,{"key":20,"text":21,"correct":14},"C","施工技术的选用",{"key":23,"text":24,"correct":14},"D","经济激励措施的效力","2021\u002F2020教材P150页 施工方进度控制的管理措施涉及管理的思想、方法、手段以及承发包模式、合同类型与风险管理等。其中，工程承发包模式主要影响工程实施的组织与协调。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]