[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118730":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118730,789,1,"单选题","下列为加快施工进度而采取的各项措施中，属于技术措施的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","重视计算机软件的应用",false,{"key":16,"text":17,"correct":14},"B","编制进度控制工作流程",{"key":19,"text":20,"correct":21},"C","用大模板代替小钢模",true,{"key":23,"text":24,"correct":14},"D","实行班组内部承包制","2021\u002F2020教材P151页 (2)施工方案对工程进度有直接的影响，在决策其选用时，不仅应分析技术的先进性和经济合理性，还应考虑其对进度的影响。在工程进度受阻时，应分析是否存在施工技术的影响因素，为实现进度目标有无改变施工技术、施工方法和施工机械的可能性。C项属于改变施工方法。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]