[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118729":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118729,789,1,"单选题","施工方案对工程进度有直接的影响，在决策其选用时，不仅应分析技术的先进性和经济合理性，还应考虑其对（）的影响。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进度",true,{"key":16,"text":17,"correct":18},"B","质量",false,{"key":20,"text":21,"correct":18},"C","成本",{"key":23,"text":24,"correct":18},"D","安全","2021\u002F2020教材P151页 （2）施工方案对工程进度有直接的影响，在决策其选用时，不仅应分析技术的先进性和经济合理性，还应考虑对进度的影响。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]