[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118728":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118728,789,1,"单选题","业主方项目进度控制的任务是控制（）的进度。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目全寿命周期",false,{"key":16,"text":17,"correct":18},"B","整个项目实施阶段",true,{"key":20,"text":21,"correct":14},"C","项目施工阶段",{"key":23,"text":24,"correct":14},"D","整个项目决策阶段","2021\u002F2020教材P128页 业主方项目进度控制的任务是控制整个项目实施阶段的进度。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]