[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118727":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118727,789,1,"单选题","下列措施中属于进度控制组织措施的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","定义施工进度计划系统的组成",true,{"key":16,"text":17,"correct":18},"B","采用工程网络计划的方法编制进度计划",false,{"key":20,"text":21,"correct":18},"C","编制与进度计划相适应的资源需求计划",{"key":23,"text":24,"correct":18},"D","改变施工技术、施工方法","2021\u002F2020教材P150页 施工方进度控制的组织措施如下。(4)应编制施工进度控制的工作流程，如①定义施工进度计划系统（由多个相互关联的施工进度计划组成的系统）的组成。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]