[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118725":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118725,789,1,"单选题","下列进度控制措施中，属于施工方进度控制的管理措施的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","编制施工进度控制的工作流程",false,{"key":16,"text":17,"correct":18},"B","用工程网络计划的方法编制进度计划",true,{"key":20,"text":21,"correct":14},"C","考虑加快工程进度所需要的资金",{"key":23,"text":24,"correct":14},"D","选用对实现施工进度目标有利的施工技术","2021\u002F2020教材P150页 施工方进度控制的管理措施如下： (2)用工程网络计划的方法编制进度计划必须很严谨地分析和考虑工作之间的逻辑关系，通过工程网格的计算可发现关键工作和关键路线，也可知道非关键工作可使消用的时差，工程网络计划的方法有利于实现进度控制的科学化。 A组织措施；C经济措施；D技术措施。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]