[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118724":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118724,789,1,"单选题","下列进度控制措施中，属于管理措施的是()",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","编制施工进度控制的工作流程",false,{"key":16,"text":17,"correct":18},"B","应用互联网进行进度计划",true,{"key":20,"text":21,"correct":14},"C","制定进度控制工作流程",{"key":23,"text":24,"correct":14},"D","选择先进的施工技术","2021\u002F2020教材P150页 施工方进度控制的管理措施：应重视信息技术（包括相应的软件、局域网、互联网以及数据处理设备等）在进度控制中的应用。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]