[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118722":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118722,789,1,"单选题","施工进度控制在管理观念方面存在的主要问题不包括（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","缺乏静态控制的观念",true,{"key":16,"text":17,"correct":18},"B","缺乏动态控制的观念",false,{"key":20,"text":21,"correct":18},"C","缺乏进度计划系统的观念",{"key":23,"text":24,"correct":18},"D","缺乏进度计划多方案比较和选优的观念","2021\u002F2020教材P150页 二、施工方进度控制的管理措施：1.缺乏进度计划系统的观念；2.缺乏动态控制的观念；3.缺乏进度计划多方案比较和优选的观念。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]