[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118717":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118717,789,1,"单选题","施工方进度控制管理措施涉及管理的思想、方法、手段以及承发包模式、合同类型与风险管理等，其中，工程承发包模式主要影响（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工作之间的逻辑关系",false,{"key":16,"text":17,"correct":18},"B","工程实施的组织与协调",true,{"key":20,"text":21,"correct":14},"C","施工技术的选用",{"key":23,"text":24,"correct":14},"D","经济激励措施的效力","2021\u002F2020教材P150页 （3）承发包模式的选择直接关系到工程实施的组织和协调。为了实现进度目标，应选择合理的合同结构，以避免过多的合同交界面而影响工程的进展。工程物资的采购模式对进度也有直接的影响，对此应作比较分析。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]