[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118716":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118716,789,1,"单选题","施工进度计划的调整应包括工作（工序）起止时间的调整、工作关系的调整、资源提供条件、必要的目标的调整以及（）的调整。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工管理组织",false,{"key":16,"text":17,"correct":14},"B","合同约定工期",{"key":19,"text":20,"correct":21},"C","工程量",true,{"key":23,"text":24,"correct":14},"D","施工技术方案","2021\u002F2020教材P149页 施工进度计划的调整应包括下列内容：工程量、工作（工序）起止时间、工作关系、资源提供条件、必要目标的调整。这些调整的内容按照网络计划编制需要的各项参数而设定的。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]