[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118715":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118715,789,1,"单选题","施工进度计划的调整应包括工程量、工作（工序）起止时间、资源提供条件、必要的目标以及（）的调整。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工作关系",true,{"key":16,"text":17,"correct":18},"B","技术方案",false,{"key":20,"text":21,"correct":18},"C","工作量",{"key":23,"text":24,"correct":18},"D","管理措施","2021\u002F2020教材P149页 施工进度计划的调整应包括下列内容：工程量、工作（工序）起止时间、工作关系、资源提供条件、必要目标的调整。这些调整的内容按照网络计划编制需要的各项参数而设定的",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]