[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118713":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118713,789,1,"单选题","下列影响建设工程项目管理目标实现的因素中，起决定性作用的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","人",false,{"key":16,"text":17,"correct":14},"B","方法",{"key":19,"text":20,"correct":14},"C","工具",{"key":22,"text":23,"correct":24},"D","组织",true,"2021\u002F2020教材P149页 组织是目标能否实现的决定性因素，因此，为实现项目的进度目标，应充分重视健全项目管理的组织体系",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]