[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118712":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118712,789,1,"单选题","施工进度计划实施时，将实际数据与进度计划对比之后应进行的工作是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","跟踪检查，收集实际进度数据",false,{"key":16,"text":17,"correct":14},"B","进度计划的变更必须与有关单位和部门及时沟通",{"key":19,"text":20,"correct":14},"C","检查措施的落实情况",{"key":22,"text":23,"correct":24},"D","分析计划执行的情况",true,"2021\u002F2020教材P149页 在进度计划实施过程中，应进行工作：（1）跟踪检查，收集实际数据；（2）将实际数据与进度计划对比；（3）分析计划执行情况；（4）对产生的进度计划采取措施予以纠正或调整计划；（5）检查措施落实情况；（6）进度计划的变更必须与有关部门及时沟通。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]