[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118711":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118711,789,1,"单选题","关于建设工程项目进度控制的说法,不正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","各参与方都有进度控制的任务",false,{"key":16,"text":17,"correct":18},"B","项目实施过程中不允许调整进度计划",true,{"key":20,"text":21,"correct":14},"C","进度控制是一个动态的管理过程",{"key":23,"text":24,"correct":14},"D","进度目标的分析论证是进度控制的一个环节","2021\u002F2020教材P149页 选项B项目实施过程中允许调整进度计划。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]