[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118710":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118710,789,1,"单选题","施工进度计划检査后,应编制进度报告,其内容不包括()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","进度计划实施情況的综合描述",false,{"key":16,"text":17,"correct":14},"B","实际工程进度与计划进度的比较",{"key":19,"text":20,"correct":21},"C","前一次进度计划检査提出问题的整改情况",true,{"key":23,"text":24,"correct":14},"D","进度计划在实施过程中存在的问题及其原因分析","2021\u002F2020教材P149页 施工进度计划检査后应按下列内容编制进度报告:进度计划实施情况的综合描述;实际工程进度与计划进度的比较;进度计划的实施过程中存在的问题,及其原因分析;进度执行情况对工程质量、安全和施工成本的影响情况;将采取的措施;进度的预测。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]