[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118709":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118709,789,1,"单选题","在施工进度计划实施过程中，应有序进行下列工作：①跟踪检查，收集实际进度数据；②；③分析计划执行的情况；④对进度的变化采取措施予以纠正或调整计划；⑤检查措施的落实情况；⑥进度计划的变更必须与有关单位和部门及时沟通。其中，第②的工作是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","编制施工进度计划",false,{"key":16,"text":17,"correct":14},"B","收集施工进度计划数据",{"key":19,"text":20,"correct":14},"C","落实施工管理组织",{"key":22,"text":23,"correct":24},"D","将实际数据与进度计划对比",true,"2021\u002F2020教材P149页 施工进度计划的实施指的是按进度计划的要求组织人力、物力和财力进行施工。在进度计划的实施过程中，跟踪检查，收集实际进度数据之后紧接着的是将实际数据与进度计划进行比较。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]