[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118708":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118708,789,1,"单选题","下列不属于施工进度计划的调整内容的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程量",false,{"key":16,"text":17,"correct":18},"B","工程质量",true,{"key":20,"text":21,"correct":14},"C","工作关系",{"key":23,"text":24,"correct":14},"D","必要目标","2021\u002F2020教材P149页 施工进度计划的调整应包括下列内容：①工程量的调整；②工作（工序）起止时间的调整；③工作关系的调整；④资源提供条件的调整；⑤必要目标的调整。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]