[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118706":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118706,789,1,"单选题","依据施工承包合同，施工方为确保工程进度按合同如期完成，需对工程施工进度进行有效控制。施工进度控制主要环节包括：①编制施工进度计划；②组织施工进度计划实施；③编制资源需求计划；④施工进度计划检查与调整。控制顺序正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①②③④",false,{"key":16,"text":17,"correct":18},"B","①③②④",true,{"key":20,"text":21,"correct":14},"C","③①②④",{"key":23,"text":24,"correct":14},"D","③①④②","2021\u002F2020教材P148页 施工方进度控制的主要工作环节包括：⑴编制施工进度计划及相关的资源需求计划⑵组织施工进度计划的实施⑶施工进度计划的检查与调整。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]