[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118705":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118705,789,1,"单选题","下列建设工程项目进度控制工作中，属于施工方进度控制任务的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","部署项目动用准备工作进度",false,{"key":16,"text":17,"correct":14},"B","协调设计、招标的工作进度",{"key":19,"text":20,"correct":21},"C","编制项目施工的工作计划",true,{"key":23,"text":24,"correct":14},"D","编制供货进度计划","2021\u002F2020教材P148页 施工方进度控制的主要工作环节包括：(1)编制施工进度计划及相关的资源需求计划；(2)组织施工进度计划的实施；(3)施工进度计划的检査与调整。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]