[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118704":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118704,789,1,"单选题","施工方进度控制的主要工作环节不包括（）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","编制施工进度计划及相关的资源需求计划",false,{"key":16,"text":17,"correct":14},"B","组织施工进度计划的实施",{"key":19,"text":20,"correct":14},"C","施工进度计划的检查与调整",{"key":22,"text":23,"correct":24},"D","施工进度计划的核实",true,"2021\u002F2020教材P148页 施工方进度控制的主要工作环节包括：(1)编制施工进度计划及相关的资源需求计划；(2)组织施工进度计划的实施；(3)施工进度计划的检查与调整。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]