[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118702":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118702,789,1,"单选题","在某工程网络计划中，工作M的最早开始时间为第15天，其持续时间为7天。工作M有两项紧后工作，它们的最早开始时间分别为第27天和第30天，最迟完成时间分别为第36天和第42天，工作持续时间分别为8和9，则工作M的总时差和自由时差()天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","均为5",false,{"key":16,"text":17,"correct":18},"B","分别为6和5",true,{"key":20,"text":21,"correct":14},"C","分别为11和6",{"key":23,"text":24,"correct":14},"D","均为6","2021\u002F2020教材P141页 总时差等于其最迟开始时间减去最早开始时间，或等于最迟完成时间减去最早完成时间。自由时差等于紧后工作的最早开始时间减去本工作的最早完成时间。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]