[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118700":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118700,789,1,"单选题","在网络计划中，若某项工作的()最小，则该工作必为关键工作。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","自由时差",false,{"key":16,"text":17,"correct":14},"B","持续时间",{"key":19,"text":20,"correct":14},"C","时间间隔",{"key":22,"text":23,"correct":24},"D","总时差",true,"2021\u002F2020教材P148页 关键工作是指网络计划中总时差最小的工作。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]