[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118698":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118698,789,1,"单选题","在不影响总工期的前提下，本工作可以利用的机动时间是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总时差",true,{"key":16,"text":17,"correct":18},"B","自由时差",false,{"key":20,"text":21,"correct":18},"C","时距",{"key":23,"text":24,"correct":18},"D","时间间隔","2021\u002F2020教材P148页 总时差指的是在不影响总工期的前提下，可以利用的机动时间。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]