[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118696":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118696,789,1,"单选题","在工程网络计划执行过程中，当某项工作的最早完成时间推迟天数超过其自由时差时，将会影响（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","该工作平行工作的最早开始时间",false,{"key":16,"text":17,"correct":18},"B","该工作紧后工作的最早开始时间",true,{"key":20,"text":21,"correct":14},"C","本工作的最迟完成时间",{"key":23,"text":24,"correct":14},"D","该工作紧后工作的最迟完成时间","2021\u002F2020教材P148页 自由时差指的是在不影响其紧后工作最早开始时间的前提下，本工作可以利用的机动时间。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]