[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118695":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118695,789,1,"单选题","关于利用网络计划中工作自由时差的说法，正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不会影响紧后工作，也不会影响总工期",true,{"key":16,"text":17,"correct":18},"B","不会影响紧后工作，但会影响总工期",false,{"key":20,"text":21,"correct":18},"C","会影响紧后工作，但不会影响总工期",{"key":23,"text":24,"correct":18},"D","会影响紧后工作，也会影响总工期","2021\u002F2020教材P148页 自由时差指的是在不影响其紧后工作最早开始时间的前提下，本工作可以利用的机动时间。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]