[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118694":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118694,789,1,"单选题","关于网络计划的说法，正确的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","网络计划中允许存在循环回路",false,{"key":16,"text":17,"correct":14},"B","由关键工作组成的线路称为非关键线路",{"key":19,"text":20,"correct":21},"C","一个网络计划可能有多条关键线路",true,{"key":23,"text":24,"correct":14},"D","关键线路上也可能存在非关键工作","2021\u002F2020教材P148页 在双代号网络计划和单代号网络计划中，关键路线是总的工作持续时间最长的线路。一个网络计划可能有一条，或几条关键路线",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]