[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118692":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118692,789,1,"单选题","已知某工作的持续时间为4天，最早开始时间为7天，总时差2天，则该工作的最迟完成的时间为()天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","4",false,{"key":16,"text":17,"correct":14},"B","9",{"key":19,"text":20,"correct":14},"C","11",{"key":22,"text":23,"correct":24},"D","13",true,"2021\u002F2020教材P148页 某工作的最迟开始时间为最早开始时间加总时差（7+2=9天），则最迟完成的时间为最早开始时间加工作的持续时间（9+4=13天）。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]