[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118691":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118691,789,1,"单选题","工程网络计划中，关键工作是指()的工作。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","自由时差最小",false,{"key":16,"text":17,"correct":18},"B","总时差最小",true,{"key":20,"text":21,"correct":14},"C","时间间隔为零",{"key":23,"text":24,"correct":14},"D","开始节点和完成节点均为关键节点","2021\u002F2020教材P148页 关键工作指的是网络计划中总时差最小的工作。当计划工期等于计算工期时，总时差为零的工作就是关键工作。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]