[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118689":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118689,789,1,"单选题","已知某工程双代号网络计划的计划工期等于计算工期，且工作M的开始节点和完成节点均为关键节点，下列关于工作M说法正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","为关键工作",false,{"key":16,"text":17,"correct":18},"B","总时差等于自由时差",true,{"key":20,"text":21,"correct":14},"C","自由时差为零",{"key":23,"text":24,"correct":14},"D","总时差大于自由时差","2021\u002F2020教材P148页 当计划工期等于计算工期时，总时差为零的工作就是关键工作。总时差等于自由时差。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]