[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118688":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118688,789,1,"单选题","当工程网络图中某非关键工作拖延5天，而该工作总时差为3天，则网络计划总工期将拖延( )天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2",true,{"key":16,"text":17,"correct":18},"B","3",false,{"key":20,"text":21,"correct":18},"C","5",{"key":23,"text":24,"correct":18},"D","8","2021\u002F2020教材P148页 2Z103033关键工作、关键路线和时差总时差指的是在不影响总工期的前提下，可以利用的机动时间。本题中，该工作对总工期的影响为5-3=2天。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]