[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118687":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118687,789,1,"单选题","某工程双代号网络计划图如图所示（时间单位：天），则该计划的关键线路是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1-2-3-4-5-6",false,{"key":16,"text":17,"correct":14},"B","1-2-3-4-6",{"key":19,"text":20,"correct":21},"C","1-3-4-6",true,{"key":23,"text":24,"correct":14},"D","1-3-5-6","2021\u002F2020教材P148页 2Z103033关键工作、关键路线和时差在双代号网络计划和单代号网络计划中，关键路线是总的工作持续时间最长的线路。一个网络计划可能有一条，或几条关系路线，在网络计划执行过程中，关键路线有可能转移。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]