[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118686":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118686,789,1,"单选题","下列关于工程网络计划关键工作的表述中，正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","双代号时标网络计划中关键工作没有波形线",true,{"key":16,"text":17,"correct":18},"B","单代号网络计划中的关键工作与其紧后工作之间的时间间隔为零",false,{"key":20,"text":21,"correct":18},"C","工程网络计划中的关键工作的总时差一定为零",{"key":23,"text":24,"correct":18},"D","双代号网络计划中的关键工作必定全在关键线路上","2021\u002F2020教材P146页 B错在单代号网络图中关键线路工作与紧后工作之间的时间间隔不一定是0。C错在，是关键线路上总时差一定为0，关键工作的总时差不一定为0。D错在关键工作不一定都在关键线路上。 从起点节点开始到终点节点均为关键工作,且所有工作的时间间隔为零的线路关键线路.总时差最小的工作是关键工作. @##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]