[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118685":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118685,789,1,"单选题","在工程网络计划中，关键线路是指()的线路。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","单代号网络计划中由关键工作组成",false,{"key":16,"text":17,"correct":14},"B","双代号网络计划中由关键点组成",{"key":19,"text":20,"correct":14},"C","双代号时标网络计划中有波形线",{"key":22,"text":23,"correct":24},"D","单代号网络计划中时间间隔均为零",true,"2021\u002F2020教材P146页 单代号网络计划中关键线路的确定按以下规定，从起点节点开始到终点节点均为关键工作，且所有工作时间间隔为零的线路为关键线路。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]