[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118684":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118684,789,1,"单选题","关于工程网络计划中关键工作判别的说法，正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","与紧前工作之间时间间隔为零的工作是关键工作",false,{"key":16,"text":17,"correct":18},"B","总时差最小的工作为关键工作",true,{"key":20,"text":21,"correct":14},"C","与紧后工作之间时间间隔为零的工作是关键工作",{"key":23,"text":24,"correct":14},"D","最迟开始时间与最早开始时间之差最大的工作是关键工作","2021\u002F2020教材P146页 (1)关键工作：总时差最小的工作是关键工作。(2)关键线路的确定按以下规定：从起点节点开始到终点节点均为关键工作，且所有工作的时间间隔为零的线路为关键线路。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]