[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118683":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118683,789,1,"单选题","在工程网络计划中，关键工作是指网络计划中()",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总时差为零的工作",false,{"key":16,"text":17,"correct":18},"B","总时差最小的工作",true,{"key":20,"text":21,"correct":14},"C","在不影响紧后工作最早开工的前提下机动时间为零的工作",{"key":23,"text":24,"correct":14},"D","持续时间最长的工作","2021\u002F2020教材P141页 网络计划中总时差最小的工作是关键工作。总时差为零的工作是关键工作，前提是当计划工期等于计算工期时。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]