[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118682":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118682,789,1,"单选题","单代号网络图中工作的最早开始时间等于( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","该工作的各个紧前工作的最早完成时间的最大值",true,{"key":16,"text":17,"correct":18},"B","该工作的各个紧前工作的最早完成时间的最小值",false,{"key":20,"text":21,"correct":18},"C","该工作的最早开始时间加该工作的持续时间",{"key":23,"text":24,"correct":18},"D","该工作的最迟开始时间减该工作的自由时差","2021\u002F2020教材P145页 1.计算最早开始时间和最早完成时间工作最早开始时间等于该工作的各个紧前工作的最早完成时间的最大值。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]