[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118681":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118681,789,1,"单选题",".对于单代号网络图的绘图规则，下列叙述中错误的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","单代号网络图中只应有一个起点节点和一个终点节点",false,{"key":16,"text":17,"correct":14},"B","单代号网络图中，严禁出现双向箭头或无箭头的连线",{"key":19,"text":20,"correct":21},"C","单代号网络图中，允许出现循环回路",true,{"key":23,"text":24,"correct":14},"D","绘制网络图时，箭线不宜交叉，当交叉不可避免时，可采用过桥法或指向法绘制","2021\u002F2020教材P145页 （三）单代号网络图的绘图规则（2）单代号网络图中，严禁出现循环回路。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]