[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118677":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118677,789,1,"单选题","下列关于单代号网络图与双代号网络图特点的说法，错误的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","两种网络图中工作都可以用虚箭头表示",true,{"key":16,"text":17,"correct":18},"B","单代号网络图中不使用虚箭头和虚工作",false,{"key":20,"text":21,"correct":18},"C","双代号网络图的持续时间不是表示在节点之中的",{"key":23,"text":24,"correct":18},"D","单代号网络图工作之间的逻辑关系会产生更多的纵横交叉现象","2021\u002F2020教材P144页 单代号网络图与双代号网络图相比，具有以下特点： 1.工作之间的逻辑关系容易表达，且不用虚箭线，故绘图较简单； 2.网络图便于检査和修改； 3.由于工作持续时间表示在节点之中，没有长度，故不够形象直观； 4.表示工作之间逻辑关系的箭线可能产生较多的纵横交叉现象。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]