[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118676":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118676,789,1,"单选题","已知单代号网络计划中，工作A最早开始时间(ES)和最早完成时间(E F)分别为10天和24天，则其紧后工作B的最早开始时间(ES2)和最早完成时间（EF2）分别为()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","10天和18天",false,{"key":16,"text":17,"correct":14},"B","18天和32天",{"key":19,"text":20,"correct":14},"C","18天和24天",{"key":22,"text":23,"correct":24},"D","24天和32天",true,"2021\u002F2020教材P142页 工作B的最早开始时间(ES2)等于工作A最早完成时间(EF)为24天，工作B的最早完成时间(EF2)等于它的最早开始时间(ES2)加上持续时间为32天（24+8=32天）。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]