[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118675":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118675,789,1,"单选题","某双代号网络计划中(以天为单位)，工作K的最早开始时间为6.工作持续时间为4；工作M的最迟完成时间为22，工作持续时间为10；工作N的最迟完成时间为20，工作持续时间为5。已知工作K只有M、N两项紧后工作，工作K的总时差为()天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2",true,{"key":16,"text":17,"correct":18},"B","3",false,{"key":20,"text":21,"correct":18},"C","5",{"key":23,"text":24,"correct":18},"D","6","2021\u002F2020教材P141页 工作M的最迟开始时间为22－10=12天，工作N的最迟开始时间为20－5=15天，工作K的最迟完成时问为min{12，15}=12，所以，工作K的总时差为",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]