[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118674":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118674,789,1,"单选题","工程网络计划中,工作E有两项紧后工作G和H,已知工作G和工作H的最早开始时间分别为25和28,工作E的最早开始时间和持续时间分别为17和6,则工作E的自由时差为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":18},"B","2",true,{"key":20,"text":21,"correct":14},"C","3",{"key":23,"text":24,"correct":14},"D","5","2021\u002F2020教材P141页 工作E紧后工作的最早开始时间=min{25,28}=25,工作E最早开始时间和持续时间分别为17和6,即工作E的最早完成时间=17十6=23,所以工作E的自由时差=紧后工作的最早开始时间-本工作最早完成时间=25-23=2。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]