[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118673":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118673,789,1,"单选题","已知单代号网络计划中某工作最早开始时间和最早完成时间分别为4天和6天，最迟开始时间和最迟完成时间分别为7天和9天，则该工作的总时差为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2天",false,{"key":16,"text":17,"correct":18},"B","3天",true,{"key":20,"text":21,"correct":14},"C","4天",{"key":23,"text":24,"correct":14},"D","6天","2021\u002F2020教材P141页 总时差等于其最迟开始时间减去最早开始时间，或等于最迟完成时间减去最早完成时间。7-4或者9-6，均为3天。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]