[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118670":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118670,789,1,"单选题","在工程网络计划中，某项工作的最迟开始时间与最早开始时间的差值为该工作的()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","时间间隔",false,{"key":16,"text":17,"correct":14},"B","搭按时距",{"key":19,"text":20,"correct":14},"C","自由时差",{"key":22,"text":23,"correct":24},"D","总时差",true,"2021\u002F2020教材P141页 总时差等于其最迟开始时间减去最早开始时间，或等于最迟完成时间减去最早完成时间。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]